Gold Fields anticipates achieving the first gold pour at Windfall by late Q4 2026 or early 2027 .
Full-scale construction of the processing plant is slated to take 18–24 months. Osisko drills more high grades across Windfall ...
Windfall is ranked as a top 10 gold deposit globally by head grade, with reserves averaging 8.1 g/t gold . Gold Fields anticipates achieving the first gold pour
The site is now fully powered by hydroelectricity through an 85km power line operated by the Cree First Nation of Waswanipi , significantly reducing the project's carbon footprint. significantly reducing the project's carbon footprint.